21. The _【】 technique involves using project characteristics in a mathematical model to predict total project cost.models can be simple or complex.
    A.cost aggregation        B.reserve analysis
  C.parametric estimating     D.funding limit reconciliarion

22. 【】 is ameasurable, verifiable work poduct such as specification.feasibility study report, detail document, or working prototype
   A.milestone  B.deliverable  C.etc    D.BAC

23. 【】 are individuals and organizations that are actively involved in the project, or whose interests may be affected as aresult of project execution or project completion; they may also exert influence over the project and its results.
   A.controls          B.baselines
  C.project stakeholders    D.project managers

24.【】 is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
  A.project acceptance     B.scope verification
  C.scope definition      D.WBS Creation 

25. 信某系统集成项目的目标是使人们能在各地书报零售店购买到彩票,A公司负责开发该项目适用的软件,但需要向其他公司购买硬件设备。A公司外包管理员首先应准备的文件被称为__【】。
  A.工作说明书    B.范围说明书  C.项目章程    D.合同

相关内容

热门资讯

2013年11月软件水平《网络... 2013年11月软件水平《网络工程师》考试试题答案(网友版)
信息系统项目管理师历年考试真题... 信息系统项目管理师历年考试真题精选【9】
信息系统项目管理师历年考试真题... 信息系统项目管理师历年考试真题精选【10】
2013年11月软件水平《嵌入... 2013年11月软件水平《嵌入式系统设计师》考试试题答案(网友版)
软考程序员考试真题精选4 软考程序员考试真题精选4
软考程序员考试真题精选6 软考程序员考试真题精选6
信息系统项目管理师历年考试真题... 信息系统项目管理师历年考试真题精选【4】
信息系统项目管理师历年考试真题... 信息系统项目管理师历年考试真题精选【7】
软考网络工程师考试真题精选1 软考网络工程师考试题
软考网络工程师考试真题精选4 软考网络工程师考试真题精选4